The following is a tentative schedule for the completion of South Bowie Library.

The items in bold have been completed.

September 18, 2007

The contract to purchase the property was signed.

November 19, 2007

District Council review.

November, 2007

Contract signed with architectural firm.

May 2008

Comprehensive Design Plan approved.

May 2008

Architectural plans complete.

June 2008 

Preliminary Plan approved.

July 2008 

Construction project put out to bid

July 2008

Specific Design Plan approved.

September 2008

Final Plat of Subdivision.

November 2008

Construction Begins

April 2010

Library opens for business

 

     

 