The following is a tentative schedule for the completion of South Bowie Library.
The items in bold have been completed.
|
September 18, 2007 |
The contract to purchase the property was signed. |
|
November 19, 2007 |
District Council review. |
|
November, 2007 |
Contract signed with architectural firm. |
|
May 2008 |
Comprehensive Design Plan approved. |
|
May 2008 |
Architectural plans complete. |
|
June 2008 |
Preliminary Plan approved. |
|
July 2008 |
Construction project put out to bid |
|
July 2008 |
Specific Design Plan approved. |
|
September 2008 |
Final Plat of Subdivision. |
|
November 2008 |
Construction Begins |
|
April 2010 |
Library opens for business |